Public Health Division Bahadurgarh
|
|
Statement showing Progress report of ongoing
Development works upto 11/07 under W/S &Sanitation Division Bahadurgarh.
|
|
Sr.
No.
|
Name of Scheme
|
Name of Villages Covered
|
Pop.
2001
|
Present Status lpcd
|
Estimated
Cost
|
Funds
upto date
|
Expenditure Rs. In lacs
|
Physical Progress
|
Likely Date of Completion
|
|
Upto
3/07
|
During the Year 07-08
|
Upto
date
|
|
A)
|
DDP
|
|
1
|
Imp w/s vill Mundakhera,
|
Mundakhera
|
2123
|
55
|
75.30
|
25.00
|
0.00
|
0.00
|
0.00
|
Tender under progress
|
Mar-09
|
|
|
Asmayalpur and Fatehpur from
Badsa w/w
|
Asmayalpur
Fatehpur
|
1776
1261
|
40
55
|
|
|
|
|
|
|
|
|
|
|
Total
|
5160
|
|
|
|
|
|
|
|
|
|
2
|
B/Stn vill Lohat &Devar
Khana
|
Lohat
|
1156
|
70
|
52.22
|
17.00
|
0.00
|
0.00
|
0.00
|
Tender invited
|
Mar-09
|
|
Dever Khana
|
1027
|
70
|
|
|
|
Total
|
2183
|
|
|
|
|
|
|
|
|
|
3
|
2 No. B/Stn vill Bupania
|
Bupania
|
10085
|
70
|
70.00
|
21.00
|
0.00
|
0.00
|
0.00
|
Tender invited
|
Mar-09
|
|
4
|
Imp w/s Ladrawan & Sohti
|
Ladrawan
|
8008
|
70
|
102.80
|
43.00
|
0.00
|
0.00
|
0.00
|
Tender invited
|
Mar-09
|
|
Sohti
|
3057
|
40
|
|
|
|
Total
|
11065
|
|
300.32
|
106.00
|
0.00
|
0.00
|
0.00
|
|
|
|
B)
|
NABARD (RIDF-XII)
|
|
|
|
|
|
|
|
|
|
|
|
1
|
Aug. w/s Sch. Kheri Jatt
|
Kheri Jat
|
3316
|
25
|
60.98
|
35.40
|
0.36
|
43.03
|
43.39
|
Work of HLT repair of water works and
distribution in progress
|
Mar-09
|
|
2
|
Aug. W/S Sch. Bhaproda & Asanda
|
Bhaproda
Asanda
|
6554
|
25
|
158.32
|
92.40
|
21.43
|
89.78
|
111.21
|
Work of S&S Tank,F/Bed,
HLT & pipe line, 2 Nos. B/station in progress
|
Mar-09
|
|
2389
|
20
|
|
Total
|
9943
|
|
|
3
|
Aug. w/s Sch. Mandothi
|
Mandothi
|
10660
|
20
|
212.15
|
123.90
|
0.18
|
85.80
|
85.98
|
Work of S&S tank, F/Bed,CWT
in progress
|
Mar-09
|
|
4
|
Indp. w/s Sch. Mattan
|
Mattan
|
5172
|
70
|
178.84
|
104.40
|
12.38
|
39.17
|
51.55
|
Work of S&S tank and boundary wall
progress
|
Mar-09
|
|
5
|
Aug. w/s Sch. Faizabad, Jahangirpur
from Badli
|
Faizabad
Jahangirpur
|
4290
5430
|
20
20
|
275.57
|
160.90
|
82.54
|
6.79
|
89.33
|
Work of structures at w/w
Passour and distribution in progress
|
Mar-09
|
|
Total
|
9720
|
|
|
6
|
Aug.w/s Sch. Barahi
|
Barahi
|
5235
|
40
|
152.10
|
88.80
|
0.10
|
1.46
|
1.56
|
Work just started
|
Mar-09
|
|
7
|
Indt. w/s Sch. Chhudani
|
Chuddani
|
3038
|
20
|
134.46
|
78.50
|
0.34
|
19.49
|
19.83
|
Work of S/S Tank, FB, CWT
& B/Wall in progress.
|
Mar-09
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sr.
No.
|
Name of Scheme
|
Name of Villages Covered
|
Pop.
2001
|
Present Status lpcd
|
Estimated
Cost
|
Funds
upto date
|
Expenditure Rs. In lacs
|
Physical Progress
|
Likely Date of Completion
|
|
Upto
3/07.
|
During the
Year 07-08
|
Upto Date
|
|
8
|
Aug. w/s Sch.Dulhera
|
Dulhera
|
7304
|
25
|
114.64
|
66.80
|
0.01
|
38.74
|
38.75
|
Work of Inlet Channel in progress,
HLT,CWT Completed.
|
Mar-09
|
|
9
|
Aug. w/s Sch. Kharhar
|
Kharar
|
5172
|
70
|
97.06
|
56.60
|
0.00
|
6.26
|
6.26
|
Work just started
|
Mar-09
|
|
10
|
Aug. w/s Sch. Daboda Khurd
(Silothi)
|
Daboda
Khurd
|
4341
|
55
|
65.23
|
38.00
|
0.40
|
36.33
|
36.73
|
Work of HLT and Distribution in progress
|
Mar-09
|
|
11
|
Aug. w/s Sch. Khungai &
Kablana from w/w Goria Kalan
|
Khungai
Kablana
|
3083
5103
|
55
20
|
251.09
|
146.60
|
0.04
|
-4.98
|
-4.94
|
Work just started
|
Mar-09
|
|
Total
|
8186
|
|
|
|
Total
|
|
|
|
1700.44
|
992.30
|
117.78
|
361.87
|
479.65
|
|
|
|
C)
|
|
|
|
|
|
|
|
|
|
|
|
|
1
|
Aug. w/s Badli
|
Badli
|
13479
|
70
|
213.04
|
213.04
|
107.15
|
21.82
|
128.97
|
Work of HLT F/Bed, CWT & 3 Nos. B/Station completed and distribution in progress.
|
Mar-08
|
|
Daryapur
|
3125
|
25
|
|
Mahmoodpur
Majra
|
371
|
70
|
|
Total
|
16975
|
|
|
2
|
Aug. w/s Jassaur Kheri
|
Jasour Kheri
|
3972
|
55
|
132.38
|
132.38
|
107.55
|
41.52
|
149.07
|
Work of S/S Tank, Filter bed
& clear water tank,boundary wall completed work of distribution system in progress.
Award for land of I/C to be announced.
|
Mar-08
|
|
Kheri Jasour
|
4148
|
55
|
|
Loharheri
|
2841
|
70
|
|
Dahkora
|
2209
|
20
|
|
Total
|
13170
|
|
|
3
|
Aug. w/s Sch. Ladpur gp
|
Ladpur
|
3997
|
70
|
190.21
|
190.21
|
157.17
|
8.31
|
165.48
|
Work of S/S Tank, Filter bed
& clear water tank and
3 no boosing station completed. Work of distraction in progress
|
Mar-08
|
|
Bahmnola
|
3111
|
70
|
|
Munimpur
Kukrola
|
2139
|
70
|
|
Kaloi
|
2593
|
20
|
|
Total
|
11840
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | |