ONGOING PROJECTS > JHAJJAR PROJECTS....
|
|
|
|
3X500 ARAVALI SUPER THERMAL
POWER PROJECT, JHAJJAR:
|
|
|
|
This Coal based Super Thermal Power Project is being
Set up at Jhajjar. The Project is being executed by NTPC from concept to commissioning
and subsequent Operation & Maintenance in Joint Venture with Government of Delhi
and Government of Haryana. The MOU in this regard was signed between NTPC,
Government of National Capital Territory (NCT),
Delhi
and Government of Haryana on 24.08.2006. The
best efforts Commissioning Schedule of three Units under this Project is 35, 38
& 41 months. The Joint Venture Agreement for execution of this Project was signed
on 14.12.2006 and the Joint Venture Company i.e. Aravali Power Company
Pvt. Ltd.
for execution of this Project, was formed on 21.12.2006.
|
|
(A) PROJECT HIGHLIGHTS
|
|
|
|
|
Installed Capacity
|
3 X 500 MW
|
|
Total Estimated Cost
|
Rs 8293.92 crore
|
|
Status of Clearances :
|
|
a) Land availability
|
2231 acre
|
|
b) Water availability
|
75 cusecs on daily basis from Jawahar Lal Nehru canal
and from Jhajjar Sub Branch feeder.
|
|
c) NOC from
Haryana State
Pollution Control Board (HSPCB)
|
In process.
|
|
d) MoE&F clearance
|
Received on
8th Aug’07
|
|
e) Coal linkage
|
Coal linkage of 6.94 Million Tonne Per Annum allocated
from Mahanadi Coalfields Ltd. by Ministry of Coal, Govt. of India.
|
|
Haryana’s Share
|
750 MW
|
|
Equity contribution
|
NTPC-50%, Haryana-25%, Delhi-25%.
|
|
Expected date of LOI
|
15.06.2007
|
|
Power Availability
|
180 Lac Units Per day
|
|
|
B) PHYSICAL PROGRESS ENDING
AUGUST, 2007
|
|
|
|
Out of total requirement of about 2200 acres land
for Plant area, possession of land of 3 villages i.e Jharli, Mohanbari & Goriya
comprising of 1479 acres has been completed.
|
|
|
|
Site office has started functioning at project site,
Jharli form 16.08.07.
|
|
|
|
Letter of Intent for Steam Generator and Steam Turbine
awarded to M/s BHEL on 06.07.2007 and 14.07.2007 respectively by NTPC.
|
|
|
|
Site leveling and infrastructure package was awarded
on 31.05.2007, mobilization by contractor is in progress. Construction work of approach
road to site already commenced, excavation for reservoir started on 10.07.07.
|
|
|
|
Survey for availability of construction water and
construction power has been completed. Tenders are being issued shortly for taking
up the work.
|
|
|
|
C) FINANCIAL STATUS
|
|
|
Total Indicative estimated completed cost: Rs 8587.966
( Rs crore). The equity participation by NTPC, IPGCL & HPGCL would be in the
ratio of 50:25:25
|
|
|
|
#
|
Payment Released by HPGCL
for
|
Amount (Rs. in lacs)
|
DATE
|
|
1.
|
Preliminary expenditure like cost of site specific
studies etc.
|
76.21
|
-
|
|
2.
|
cost of land, development of site office, establishment
expenses, infrastructure works, project establishment
|
7423.79
|
31.03.2007
|
|
3.
|
cost of land, development of site office, establishment
expenses, infrastructure works, project establishment (due to increase in floor
rates of land from 16 lacs to 20 lacs per acre)
|
3683.00
|
25.05.2007
|
|
4.
|
For release of advance payment to equipment suppliers.
|
6800.00
|
25.07.2007
|
|
|
Total amount released
till date
|
17983.00
|
|
|
|
D) COMMISSIONING SCHEDULE
|
|
|
The commissioning schedule for the three 500 MW Units
under this project shall be as under:
|
|
|
1.
|
500 MW Unit-I:
|
15.04.2010
|
|
|
2.
|
500 MW Unit-II:
|
15.06.2010.
|
|
|
3.
|
500 MW Unit-III:
|
15.08.2010.
|